Industriestrasse Süd renewal

Location Stadt Zug

The starting point

Industriestrasse Süd in Zug was comprehensively renovated. During the construction period of around 20 months, some 1,000 households were directly or indirectly affected by the work. Because of the long project duration, numerous construction phases and changing traffic routing, there was a high need for information among residents and other road users.

The project at a glance

With the renovation of Industriestrasse Süd, a busy urban street space was comprehensively renewed over a longer period. The work was carried out section by section and required recurring adjustments to the construction sequence and traffic routing during delivery. Given the central location and the large affected area, continuous construction site communication that could be updated flexibly was particularly important.

Industriestrasse during surfacing: a paver on the carriageway, a bus alongside and a new manhole in the foreground.
  • Construction volume

    CHF 7.5 million

  • Construction period

    April 2024 – December 2025

  • Construction phases

    9 phases

Client
Tiefbauamt Stadt Zug
Project type
Road and civil engineering
Solution used
BDFcivory WebPlus
Solution used

Our solution

With BDFcivory, all relevant project information was bundled centrally and kept up to date throughout the construction period. Particularly important were fast communication of adjustments, a clear presentation of the construction phases and ongoing information on traffic routing and restrictions. At the same time, usage and reach could be evaluated continuously.

  • Central project information

    Project description, construction phases, contacts and current information were bundled on one central platform.

  • Broad digital reach

    The public was directed to the digital project information via letters to residents, site boards, the website, press releases and social media.

  • Construction site news over a long project period

    A total of 28 construction site news updates were sent during the construction period to keep people informed about changes and the current project status.

  • Visualisation of the construction phases

    The construction sequence and individual phases were presented clearly and updated whenever changes occurred.

  • Tracking & evaluation

    Usage, reach and feedback from the public and project stakeholders were evaluated over the entire project period.

Impact in numbers

5,750 Page views
2,998 Users
228 Subscribers
28 Construction site news
2:36 min Avg. session duration

Feedback from practice

Residents

Project stakeholders

Construction phases and restrictions at a glance

The individual construction phases and traffic routing were continuously prepared digitally and updated whenever changes occurred. This allowed residents and others affected to find out at any time about the current state of the works, upcoming restrictions and adjusted traffic routing.

Construction sequence and phases at a glance
The final state at a glance
Visualisation of the final state – Industriestrasse Süd renewal
Live product · external

Experience BDFcivory live

See how BDFcivory was used in the renovation of Industriestrasse Süd. The digital project site shows construction phases, construction site news, visualisations and ongoing project information from practical use.

Open live project External link · opens in a new tab

Planning a similar project?

We will show you how BDFcivory can communicate your construction project too – up to date, clear and close to the public.